
Revealing the original structure
With demolition and strip-out commencing in summer 2019, all blocks have now been stripped-back and demolition of both the 1970’s North Earl Street structure and Clery’s warehouse building on Earl Place is complete. Within the original 1922 building, intricate demolition has steadily progressed, stripping away the 1940’s and 1970’s interventions. This includes the removal of the atrium infill structures, the roof structure, and the upper floors behind the original Portland stone colonnaded façade. Waterman Moylan’s efficient temporary works scheme, developed in coordination with the main contractor, has been implemented to allow demolition to proceed unimpeded, whilst protecting the existing structure.
Careful planning and phasing
Temporary works, piling, demolition and construction have all been carefully planned to happen in tandem, allowing great progress to be made with the scheme moving forward in different sections of the development. The new construction elements of the scheme have now begun, seeing all new reinforced concrete cores within the atrium and perimeter of the Clery’s building, up to the new third floor level, now in place. These cores tie into the existing structure, supporting the new steel framing of the upper levels with a series of bespoke steel cast-in plates which will carry the efficient long-span cellular composite beams supporting the new floors.