Phase 1 reached a key milestone with the first scaffold drops revealing the completed façade on Block 4. Internal works are actively progressing across three blocks, while several apartments have been handed over for final snagging. ESB power has been activated for the phase, and commissioning works are underway. August 2025 saw the installation of the precast roof on Block 6, while Blocks 4 and 5 have advanced to the tower section stage. Phase 2 is progressing in line with the construction programme, with internal fit-out works underway and curtain walling currently being installed for the Block 1 retail unit.
Our team is delivering civil, traffic, structural, electrical, and mechanical engineering services for this landmark project, working in partnership with Walls Construction, OMP Architects, Doyle + O’Troithigh Landscape Architecture, and Jensen Hughes.